§ 27-209. Technical Staff Report.  


Latest version.
  • (a)

    In connection with each application, a report by the Technical Staff shall be submitted to the Planning Board for its review. The report shall contain the following:

    (1)

    The Staff's recommendation;

    (2)

    A delineation of the approximate area of the neighborhood, which shall be shown on either a Zoning Map, aerial photograph, or sketch map;

    (3)

    A description of land use and zoning in the neighborhood; and

    (4)

    In cases where the staff recommends a zone different than that requested, an analysis of the alternative zone recommended.

    (b)

    The Technical Staff Report shall be sent to all persons of record, and all other persons who request (in writing) a copy of the report. A copy of the report shall be included in the record.

    (c)

    The Technical Staff Report shall advise the reader that a hearing before the Planning Board will not be held unless the Board notifies all persons listed under Subsection (b), above.

    (d)

    The Technical Staff Report shall contain the date of the Planning Board meeting, during which the Board will decide whether to hear the case.