§ 9-123. Inspections.  


Latest version.
  • A rough-wiring inspection is required before concealment. Upon completion of an electrical installation, a request for final inspection shall be made to the Department within seventy-two (72) hours of completion. The Department shall complete any commercial electrical inspection within three (3) working days of such request.

(CB-51-1985; CB-91-2015)